It’s been 20 years since Peterborough’s historic flood

On July 15, 2004, an estimated 14 billion litres of rain fell on the city in a single day, overwhelming the city's storm water and sewer systems

On July 14 and 15, 2004, a storm dumped as much as much as 240 millimetres (9.5 inches) of rain on the City of Peterborough, with much of it falling within a five-hour period on the morning of July 15. Pictured is Charlotte St. in downtown Peterborough looking east to George St. (Photo: City of Peterborough)
On July 14 and 15, 2004, a storm dumped as much as much as 240 millimetres (9.5 inches) of rain on the City of Peterborough, with much of it falling within a five-hour period on the morning of July 15. Pictured is Charlotte St. in downtown Peterborough looking east to George St. (Photo: City of Peterborough)

Today is the 20th anniversary of Peterborough’s historic flood, when a one-in-100-year storm dumped an estimated 14 billion litres of rain on the city in a single day — the same amount of water that courses over Niagara Falls in about 40 minutes.

In 2004, as much as 240 millimetres (9.5 inches) of rain fell in the city from the evening of Wednesday, July 14th to the morning of Thursday, July 15th, most of it falling within a five-hour period on the morning of July 15.

A rainfall event of that magnitude is known as a one-in-100-year storm, meaning there’s a one per cent chance of such a storm occurring in a particular location in any given year.

Advertisement - content continues below

 

 

That one-in-100-year storm began with a weather system that affected Alberta three days before. On Sunday, July 11, 2004, the City of Edmonton experienced a small but spectacular storm that dumped more than 150 mm of rain in parts of the city in less than an hour.

Mud and water poured down streets and through windows. A record flash flood washed out roads, filled underpasses, flooded basements, turned streets into rivers and intersections into lakes. Enormous water pressure in the sewer system blew hundreds of manhole covers into the sky.

That same storm system slowly worked its way east across Canada, travelling 2,700 kilometres until it reached Peterborough. There, fed by cool air from the north and moist air from the south, the system produced intense rainstorms that began on Wednesday evening and continued for five hours during the early morning hours of Thursday.

King St. and George St. N. in downtown Peterborough on July 15, 2004. Water from Jackson Creek took over the downtown, flooding the streets and lower-level businesses and basements. (Photo: City of Peterborough)
King St. and George St. N. in downtown Peterborough on July 15, 2004. Water from Jackson Creek took over the downtown, flooding the streets and lower-level businesses and basements. (Photo: City of Peterborough)

The amount of rain that fell on Peterborough during the storm varied, from 100 mm (4 inches) recorded at the Peterborough Airport to 240 mm (9.5 inches) recorded at Trent University. Much of the rain fell in under five hours early Thursday morning, with 78.8 mm (3 inches) falling between 3:30 a.m. and 4:30 a.m. alone.

Peterborough’s drain and sewer system was unable to cope with that much storm water. Normally, the city’s sewage system deals with about 1.3 million gallons per day; during the storm, the sewage treatment plant measured a peak flow of seven million gallons of waste water.

At the time of the storm, over 80 per cent of the pipes in the city’s storm water system were undersized and didn’t meet modern standards (some had been built in the prior century), creating bottlenecks in moving the flood water.

Advertisement - content continues below

 

 

Downtown Peterborough, where the rainfall was concentrated, consists of largely impervious paved surfaces, including streets that are not well designed to convey flood water over land. Raging flood waters from Jackson Creek, which runs through the downtown, overwhelmed not only the roads but also some historical buildings.

Throughout the city, groundwater that seeped into cracked or misaligned sewer pipes created excess water in the system, leading to back-ups and basement flooding.

Peterborough’s Fire Department was inundated with calls from across the entire city, ranging from flooded basements to fire alarms. City utility and social services were overburdened with responding to the consequences of the flooding.

Hunter St. W and Aylmer St. N. in downtown Peterborough on July 15, 2004. Construction projects were halted across the city, with construction sites requiring significant cleanup after the flood. (Photo: City of Peterborough)
Hunter St. W and Aylmer St. N. in downtown Peterborough on July 15, 2004. Construction projects were halted across the city, with construction sites requiring significant cleanup after the flood. (Photo: City of Peterborough)

On Thursday morning, then-Mayor Sylvia Sutherland declared a state of emergency, which stayed in effect for two weeks. Many city staff worked 18- to 20-hour days until the state of emergency was lifted.

Here are some interesting facts about the impact of the flood:

  • 171 long-term care residents were evacuated from Extendicare Nursing Home to the Evinrude Centre
  • 500 homes and businesses had hydro meters pulled from flooded basements
  • Hundreds of flood-damaged water heaters required replacement
  • 1,000 homes had gas lines disconnected
  • 498 electrical systems were disconnected
  • There were 28 motor vehicle accidents
  • The city issued emergency clothing to more than 1,300 people and emergency food to more than 1,000 households
  • The Salvation Army served over 10,000 meals
  • Firefighters pumped out over 1,868 basements, garages, and backyards
  • 25 people who were trapped in or on cars needed to be rescued
  • Cleaning up flood-related garbage and debris was a major undertaking. Around 12,500 tons of materials were placed in the landfill in the two weeks following the flood (four times the normal amount)
  • Both the Peterborough Public Library and the adjoining Peterborough Museum and Archives were flooded, with 10 per cent of documents, photographs, and negatives in the conservation area and storage vault under water for 24 hours.
Advertisement - content continues below

 

 

In the end, the flood resulted in $95 million in insured losses in Peterborough, according to the Insurance Bureau of Canada. Overtime and expenses for city staff responding to the flood amounted to $1.4 million.

Costs of repairs and restoration (including roads, bridges, culverts, buildings, and the Museum photo archives) equalled $21 million. In addition, the Province of Ontario provided $25 million for emergency repair and restoration costs for city infrastructure. The amount of revenue and productivity that businesses and residents lost because of the flood can only be estimated.

Making matters worse, the 2004 flood came only 25 months after another major flood in June 2002, when Peterborough suffered through a severe summer storm that generated more than 70 mm (3 inches) of rain in a 24-hour period. Many Peterborough residents and business owners had just recovered from damages caused by the 2002 flood when they were hit again by the 2004 flood.

Townsend St. and George St. N. in downtown Peterborough on July 15, 2004, showing the raging flood waters from Jackson Creek emptying into Little Lake. (Photo: City of Peterborough)
Townsend St. and George St. N. in downtown Peterborough on July 15, 2004, showing the raging flood waters from Jackson Creek emptying into Little Lake. (Photo: City of Peterborough)

Shortly after the 2004 flood, the City of Peterborough hired UMA Engineering Ltd. (now known as AECOM Ltd.) to prepare a Flood Reduction Master Plan (FRMP). Since the completion of the plan in 2005, the city undertook a series of studies to assess vulnerability and to update stormwater management designs and infrastructure to protect the city from future flooding damage.

Following the flood, the city completed numerous projects, including studies recommended by the FRMP, diversion projects, storm sewer retrofits, and culvert replacements.

The highest-priority project to come out of all the flood reduction studies was the Central Area (Bethune Street) Flood Reduction project to install a massive storm sewer and upgraded sanitary sewers under Bethune Street between Jackson Creek and Townsend Street to carry high flows from the creek around the downtown core to Little Lake. One of the largest infrastructure projects in Peterborough’s history, construction began in 2019 and was largely completed by September 2023.

Advertisement - content continues below

 

 

The scope of the work included building an inlet for the storm sewer on Jackson Creek, the storm sewer outlet at Little Lake, rehabilitating the bridge under George Street at the outlet, the big dig and installation of the storm sewer under Bethune and Townsend streets, and upsizing the sanitary sewer.

While the underground work was the main component of the project, a secondary aspect was the streetscape design with the rebuilding of Bethune Street after the underground work to create a street with a greater emphasis on pedestrians and cycling but still maintaining access for vehicles.

The total cost of the project was $53.5 million, which included $7.97 million from the federal government and $7.97 million from the provincial government from the Small Communities Fund for climate adaptation projects.

Chesterfield Ave. in Peterborough on July 15, 2004. Some residents found their entire yards fully submerged by the flood waters, causing significant property damage. The Insurance Bureau of Canada says the flood resulted in $95 million in insured losses in Peterborough. (Photo: City of Peterborough)
Chesterfield Ave. in Peterborough on July 15, 2004. Some residents found their entire yards fully submerged by the flood waters, causing significant property damage. The Insurance Bureau of Canada says the flood resulted in $95 million in insured losses in Peterborough. (Photo: City of Peterborough)

In addition to upgrading infrastructure, the city continues to offer financial incentives to encourage the disconnection of foundation drains from the sanitary sewer system, use of rain barrels, the installation of backwater valves in previously affected areas, and the creation of rain gardens.

For more information about the 2004 flood and the City of Peterborough’s response to it, visit the city’s website at peterborough.ca/2004flood.

For more information on how the City of Peterborough now prepares for flooding and mitigates the potential for flooding, visit the Emergency Services – Flooding and Water and Sewers – Flood Reduction pages on the city’s website, with the latter including information about the city’s Flood Reduction Subsidy Program and Flood Reduction Master Plan.

The highest-priority project to come out of all flood reduction studies following the 2004 flood was the Central Area (Bethune Street) Flood Reduction project, which was substantially completed in September 2023. One of the largest infrastructure projects in Peterborough's history, it involved installing a massive storm sewer and upgraded sanitary sewers under Bethune Street between Jackson Creek and Townsend Street to carry high flows from the creek around the downtown core to Little Lake. (Photo: City of Peterborough)
The highest-priority project to come out of all flood reduction studies following the 2004 flood was the Central Area (Bethune Street) Flood Reduction project, which was substantially completed in September 2023. One of the largest infrastructure projects in Peterborough’s history, it involved installing a massive storm sewer and upgraded sanitary sewers under Bethune Street between Jackson Creek and Townsend Street to carry high flows from the creek around the downtown core to Little Lake. (Photo: City of Peterborough)